Friday, December 19, 2014
Stepped Foundations
Foundations - Calculated Sizing
Therefore a foundation width of 500 mm is adequate. Note: This example assumes the site is sheltered. If it is necessary to make allowance for wind loading, reference should be made to BS 6399-2: Code of practice for wind loads.
Thursday, December 4, 2014
Foundations - Basic Sizing
1. Load being transmitted, max 70 kN/m (dwellings up to 3 storeys).
2. Bearing capacity of subsoil under proposed foundation.
Bearing capacities for different types of subsoils may be obtained from tables such as those in BS 8004: Code of practice for foundations and BS 8103-1: Structural design of low rise buildings. Also, directly from soil investigation results.
The above widths may not provide adequate working space within the excavation and can be increased to give required space.
Tuesday, December 2, 2014
Foundation Beds - Typical Example
Foundation Types
DEEP STRIP OR TRENCH FILL
SOLID SLAB RAFT
BEAM AND SLAB RAFT
ISOLATED PAD
COMBINED PAD
Wednesday, November 19, 2014
Foundation Materials
Concrete is a mixture of cement - aggregates - water in controlled proportions.
Foundations - Cracking in Walls
1. The cause of cracking, i.e.
* Loads applied externally (tree roots, subsoil movement).
* Climate/temperature changes (thermal movement).
* Moisture content change (faulty dpc, building leakage).
* Vibration (adjacent work, traffic).
* Changes in physical composition (salt or ice formation).
* Chemical change (corrosion, sulphate attack).
* Biological change (timber decay).
2. The effect on a building's performance (structural and environmental).
3. The nature of movement † completed, ongoing or intermittent (seasonal).
Observations over a period of several months, preferably over a full year, will determine whether the cracking is new or established and whether it is progressing. Simple method for monitoring cracks.
Tuesday, November 18, 2014
Foundations - Subsoil Movements
Wednesday, August 27, 2014
Foundations Example
Subsoil beneath foundation is compressed and reacts by exerting an upward pressure to resist foundation loading. If foundation load exceeds maximum passive pressure of ground (i.e. bearing capacity) a downward movement of the foundation could occur. Remedy is to increase plan size of foundation to reduce the load per unit area or alternatively reduce the loadings being carried by the foundations.
Power Float
The advantages offset against the cost of plant hire are:
* Eliminates the time and materials needed to apply a finishing screed.
* A quicker process and less labour-intensive than hand troweling.
Wednesday, July 16, 2014
Poker Vibrators
Poker vibrators should be inserted vertically and allowed to penetrate 75 mm into any previously vibrated concrete.
Clamp or Tamping Board Vibrators
Placing Concrete
Monday, July 7, 2014
Concrete Pumps
The pump is supplied with pumpable concrete by means of a constant flow of ready mixed concrete lorries throughout the pumping period after which the pipeline is cleared and cleaned. Usually a concrete pump and its operator(s) are hired for the period required.
CONCRETING
1 . Material Supply and Storage - this is the receiving on site of the basic materials namely cement, fine aggregate and coarse aggregate and storing them under satisfactory conditions. (see Concrete Production † Materials on pages 284 & 285)
2. Mixing - carried out in small batches this requires only simple hand held tools whereas when demand for increased output is required mixers or ready mixed supplies could be used.
3. Transporting - this can range from a simple bucket to barrows and dumpers for small amounts. For larger loads, especially those required at high level, crane skips could be used:
For the transportation of large volumes of concrete over a limited distance concrete pumps could be used.
4. Placing Concrete - this activity involves placing the wet concrete in the excavation, formwork or mould; working the concrete between and around any reinforcement; vibrating and/ or tamping and curing in accordance with the recommendations of BS 8110: Structural use of concrete. This standard also covers the striking or removal of the formwork. Further ref. BS 8000-2.1: Workmanship on building sites. Code of practice for concrete work. Mixing and transporting concrete. Also, BS EN 1992-1-1 and -2: Design of concrete structures.
Wednesday, July 2, 2014
Tower Cranes
1. Self Supporting Static Tower Cranes † high lifting capacity with the mast or tower fixed to a foundation base - they are suitable for confined and open sites. (see page 194)
2. Supported Static Tower Cranes † similar in concept to self supporting cranes and are used where high lifts are required, the mast or tower being tied at suitable intervals to the structure to give extra stability. (see page 195)
3. Travelling Tower Cranes † these are tower cranes mounted on power bogies running on a wide gauge railway track to give greater site coverage - only slight gradients can be accommodated therefore a reasonably level site or specially constructed railway support trestle is required. (see page 196)
4. Climbing Cranes † these are used in conjunction with tall buildings and structures. The climbing mast or tower is housed within the structure and raised as the height of the structure is increased. Upon completion the crane is dismantled into small sections and lowered down the face of the building. (see page 197)
All tower cranes should be left in an `out of service' condition when unattended and in high wind conditions, the latter varying with different models but generally wind speeds in excess of 60 km p.h. would require the crane to be placed in an out of service condition thus:
Mast Cranes
Thursday, June 26, 2014
Gantry Cranes
1 . Transverse by moving along the cross beam.
2. Vertical by raising and lowering the hoist block.
3. Horizontal by forward and reverse movements of the whole gantry crane.
Track Mounted Cranes
Lorry Mounted Lattice Jib Cranes
Tuesday, June 17, 2014
Lorry Mounted Cranes
Self Propelled Cranes
Cranes - Construction
Tuesday, June 10, 2014
Rubble Chutes - Demolition
In purpose designed format, the tapered cylinders are produced from reinforced rubber with chain linkage for continuity. Overall unit lengths are generally 1100 mm, providing an effective length of 1 m. Hoppers and side entry units are made for special applications.
Ref. Highways Act - written permit (licence) must be obtained from the local authority highways department for use of a skip on a public thoroughfare. It will have to be illuminated at night and may require a temporary traffic light system to regulate vehicles.
Hoists
Fork Lift Trucks
Thursday, May 29, 2014
Dumpers - Transport Vehicles
Special format dumpers fitted with flat platforms, rigs to carry materials skips and rigs for concrete skips for crane hoisting are also obtainable. These machines are designed to traverse rough terrain but they are not designed to carry passengers and this misuse is the cause of many accidents involving dumpers.
Multi-purpose Excavators - Construction Machinery
Typical Multi-purpose Excavators Details
Draglines - Construction Machinery
Typical Dragline Details
Monday, May 19, 2014
Backacters - Construction Machinery
Typical Backacter Details
Face Shovels - Construction Machinery
Typical Face Shovel Details
Skimmers - Construction Machinery
Excavating Machines - Construction Machinery
1. Universal Excavators - this category covers most forms of excavators all of which have a common factor the power unit. The universal power unit is a tracked based machine with a slewing capacity of 360 and by altering the boom arrangement and bucket type different excavating functions can be obtained. These machines are selected for high output requirements and are rope controlled.
2. Purpose Designed Excavators - these are machines which have been designed specifically to carry out one mode of excavation and they usually have smaller bucket capacities than universal excavators; they are hydraulically controlled with a shorter cycle time.
3. Multi-purpose Excavators - these machines can perform several excavating functions having both front and rear attachments. They are designed to carry out small excavation operations of low output quickly and efficiently. Multi-purpose excavators can be obtained with a wheeled or tracked base and are ideally suited for a small building firm with low excavation plant utilisation requirements.
Wednesday, May 7, 2014
Tractor Shovels - Construction Machinery
Typical Tractor Shovel Details
Graders - Construction Machinery
Two basic formats of grader are available:-
1. Four Wheeled † all wheels are driven and steered which gives the machine the ability to offset and crab along its direction of travel.
2. Six Wheeled † this machine has 4 wheels in tandem drive at the rear and 2 front tilting idler wheels giving it the ability to counteract side thrust.
Typical Grader Details
Scrapers - Construction Machinery
forwards. Scrapers are available in three basic formats:-
1. Towed Scrapers † these consist of a four wheeled scraper bowl which is towed behind a power unit such as a crawler tractor. They tend to be slower than other forms of scraper but are useful for small capacities with haul distances up to 300 00.
2. Two Axle Scrapers † these have a two wheeled scraper bowl with an attached two wheeled power unit. They are very manoeuvrable with a low rolling resistance and very good traction.
3. Three Axle Scrapers † these consist of a two wheeled scraper bowl which may have a rear engine to assist the four wheeled traction engine which makes up the complement. Generally these machines have a greater capacity potential than their counterparts, are easier to control and have a faster cycle time.
To obtain maximum efficiency scrapers should operate downhill if possible, have smooth haul roads, hard surfaces broken up before scraping and be assisted over the last few metres by a pushing vehicle such as a bulldozer.
Typical Scraper Details
Bulldozers - Construction Machinery
The main functions of a bulldozer are:-
1 . Shallow excavations up to 300 m deep either on level ground or sidehill cutting.
2. Clearance of shrubs and small trees.
3. Clearance of trees by using raised mould blade as a pusher arm.
4. Acting as a towing tractor.
5. Acting as a pusher to scraper machines.
NB. Bulldozers push earth in front of the mould blade with some side spillage whereas angledozers push and cast the spoil to one side of the mould blade.
Typical Bulldozer Details
Saturday, April 19, 2014
Builders Plant - Output and Cycle Times
Typical Example ~
Backacter with 1 m3 capacity bucket engaged in normal trench excavation in a clayey soil and discharging directly into an attendant haulage vehicle.
An allowance should be made for the bulking or swell of the solid material due to the introduction of air or voids during the excavation process
This gives a vehicle waiting overlap ensuring excavator is fully utilised which is economically desirable.
Builders Plant Costing
Advantages of Hiring Plant:
1. Plant can be hired for short periods.
2. Repairs and replacements are usually the responsibility of the hire company.
3. Plant is returned to the hire company after use thus relieving the building contractor of the problem of disposal or finding more work for the plant to justify its purchase or retention.
4. Plant can be hired with the operator, fuel and oil included in the hire rate.
Advantages of Buying Plant:
1. Plant availability is totally within the control of the contractor.
2. Hourly cost of plant is generally less than hired plant.
3. Owner has choice of costing method used.
Typical Costing Methods
Builders Plant - Economic and Maintenance Considerations
Maintenance Considerations ~ on large contracts where a number of plant items are to be used it may be advantageous to employ a skilled mechanic to be on site to carry out all the necessary daily, preventive and planned maintenance tasks together with any running repairs which could be carried out on site.
Builders Plant - General Considerations
1. Increased production.
2. Reduction in overall construction costs.
3. Carry out activities which cannot be carried out by the traditional manual methods in the context of economics.
4. Eliminate heavy manual work thus reducing fatigue and as a consequence increasing productivity.
5. Replacing labour where there is a shortage of personnel with the necessary skills.
6. Maintain the high standards required particularly in the context of structural engineering works.
Monday, March 17, 2014
Sustainable Demolition
Linear (wasteful, non-sustainable) process ~
Closed-loop (near zero waste, sustainable) process ~
Subscribe to:
Posts (Atom)