Monday, November 30, 2015
Jack Pile Underpinning
Underpinning to Walls
1. Total length of wall to be underpinned.
2. Wall loading.
3. General state of repair and stability of wall and foundation to be underpinned.
4. Nature of subsoil beneath existing foundation.
5. Estimated spanning ability of existing foundation.
Generally suitable bay lengths are:
1000 to 1500 for mass concrete strip foundations supportingwalls of traditional construction.
1500 to 3000 for reinforced concrete strip foundations supporting walls of moderate loading.
In all the cases the total sum of the unsupported lengths of wall should not exceed 25% of the total wall length.
The sequence of bays should be arranged so that working in adjoining bays is avoided until one leg of underpinning has been completed, pinned and cured sufficiently to support the wall above.
Thursday, November 26, 2015
Underpinning - General Precautions
1. Uneven Settlement this could be caused by uneven loading of the building, unequal resistance of the soil action of tree roots or cohesive soil settlement.
2. Increase in Loading this could be due to the addition of an
extra storey or an increase in imposed loadings such as that
which may occur with a change of use.
3. Lowering of Adjacent Ground usually required when
constructing a basement adjacent to existing foundations.
General Precautions before any form of underpinning work iscommenced the following precautions should be taken:
1. Notify adjoining owners of proposed works giving full details and temporary shoring or tying.
2. Carry out a detailed survey of the site, the building to be underpinned and of any other adjoining or adjacent building or structures. A careful record of any defects found should be made and where possible agreed with the adjoining owner(s) before being lodged in a safe place.
3. Indicators or `tell tales' should be fixed over existing cracks so that any subsequent movements can be noted and monitored.
4. If settlement is the reason for the underpinning works a thorough investigation should be carried out to establish the cause and any necessary remedial work put in hand before any underpinning works are started.
5. Before any underpinning work is started the loads on the building to be underpinned should be reduced as much as possible by removing the imposed loads from the floors and installing any props and/or shoring which is required.
6. Any services which are in the vicinity of the proposed underpinning works should be identified, traced, carefully exposed, supported and protected as necessary.
Pneumatic Caissons
Typical Caissons Details
Wednesday, November 4, 2015
Installing Steel Sheet Piles
Steel Sheet Piling
Subscribe to:
Posts (Atom)