Friday, December 11, 2015
'Pynford' Stool Method of Underpinning
Needle and Pile Underpinning
for traditional or jack pile underpinning techniques. The brickwork above the existing foundation must be in a sound condition since this method relies on the `arching effect' of the brick bonding to transmit the wall loads onto the needles and ultimately to the piles. The piles used with this method are usually small diameter bored piles.
Monday, November 30, 2015
Jack Pile Underpinning
Underpinning to Walls
1. Total length of wall to be underpinned.
2. Wall loading.
3. General state of repair and stability of wall and foundation to be underpinned.
4. Nature of subsoil beneath existing foundation.
5. Estimated spanning ability of existing foundation.
Generally suitable bay lengths are:
1000 to 1500 for mass concrete strip foundations supportingwalls of traditional construction.
1500 to 3000 for reinforced concrete strip foundations supporting walls of moderate loading.
In all the cases the total sum of the unsupported lengths of wall should not exceed 25% of the total wall length.
The sequence of bays should be arranged so that working in adjoining bays is avoided until one leg of underpinning has been completed, pinned and cured sufficiently to support the wall above.
Thursday, November 26, 2015
Underpinning - General Precautions
1. Uneven Settlement this could be caused by uneven loading of the building, unequal resistance of the soil action of tree roots or cohesive soil settlement.
2. Increase in Loading this could be due to the addition of an
extra storey or an increase in imposed loadings such as that
which may occur with a change of use.
3. Lowering of Adjacent Ground usually required when
constructing a basement adjacent to existing foundations.
General Precautions before any form of underpinning work iscommenced the following precautions should be taken:
1. Notify adjoining owners of proposed works giving full details and temporary shoring or tying.
2. Carry out a detailed survey of the site, the building to be underpinned and of any other adjoining or adjacent building or structures. A careful record of any defects found should be made and where possible agreed with the adjoining owner(s) before being lodged in a safe place.
3. Indicators or `tell tales' should be fixed over existing cracks so that any subsequent movements can be noted and monitored.
4. If settlement is the reason for the underpinning works a thorough investigation should be carried out to establish the cause and any necessary remedial work put in hand before any underpinning works are started.
5. Before any underpinning work is started the loads on the building to be underpinned should be reduced as much as possible by removing the imposed loads from the floors and installing any props and/or shoring which is required.
6. Any services which are in the vicinity of the proposed underpinning works should be identified, traced, carefully exposed, supported and protected as necessary.
Pneumatic Caissons
Typical Caissons Details
Wednesday, November 4, 2015
Installing Steel Sheet Piles
Steel Sheet Piling
Thursday, October 29, 2015
Typical Cofferdam Details
Concrete Production - Specification
Grade mixes: C7.5, C10, C15, C20, C25, C30, C35, C40, C45, C50, C55, and C60; F3, F4 and F5; IT2, IT2.5, and IT3.
1. Standard Mix - BS guidelines provide this for minor works or in situations limited by available material and manufacturing data. Volume or weight batching is appropriate, but no grade over C30 is recognised.
2. Prescribed Mix - components are predetermined (to a recipe) to ensure strength requirements. Variations exist to allow the purchaser to specify particular aggregates, admixtures and colours. All grades permitted.
3. Designed Mix - concrete is specified to an expected performance. Criteria can include characteristic strength, durability and workability, to which a concrete manufacturer will design and supply an appropriate mix. All grades permitted.
4. Designated Mix - selected for specific applications. General (GEN) graded 0-4, 7.5-25 N/mm2 for foundations, floors and external works. Foundations (FND) graded 2, 3, 4A and 4B, 35 N/mm2 mainly for sulphate resisting foundations.
Paving (PAV) graded 1 or 2, 35 or 45 N/mm for roads and drives.
Reinforced (RC) graded 30, 35, 40, 45 and 50 N/mm2 mainly for prestressing.
See also BS EN 206-1: Concrete. Specification, performance, production and conformity, and BS's 8500-1 and -2: Concrete.
Concrete Production - Weight (Weigh) Batching
1. Coarse aggregates - tends to push other materials out and leaves the hopper clean.
2. Cement - this is sandwiched between the other materials ,since some of the fine cement particles could be blown away if cement is put in last.
3. Sand or fine Aggregates - put in last to stabilise the fine lightweight particles of cement powder.
Typical Densities: cement - 1440 kg/m3 sand - 1600 kg/m3 coarse aggregate - 1440 kg/m3
Water/Cement Ratio: water in concrete has two functions
1. Start the chemical reaction which causes the mixture to set into a solid mass.
2. Give the mix workability so that it can be placed, tamped or
vibrated into the required position.
Very little water is required to set concrete (approximately 0.2 w/c ratio) the surplus evaporates leaving minute voids therefore the more water added to the mix to increase its workability the weaker mis the resultant concrete. Generally w/c ratios of 0.4 to 0.5 are madequate for most purposes.
Monday, October 26, 2015
Concrete Production - Volume Batching
Volume Batching: concrete mixes are often quoted by ratio such as 1 : 2 : 4 (cement : fine aggregate or sand : coarse aggregate). Cement weighing 50 kg has a volume of 0.033 m3 therefore for the above mix 2 x 0.033 (0.066 m3) of sand and 4 x 0.033 (0.132 m3) of coarse aggregate is required. To ensure accurate amounts of materials are used for each batch a gauge box should be employed its size being based on convenient handling. Ideally a batch of concrete should be equated to using 50 kg of cement per batch. Assuming a gauge box 300 mm deep and 300 mm wide with a volume of half the required sand the gauge box size would be - volume = length x width x depth = length x 300 x 300
For the above given mix fill gauge box once with cement, twice with sand and four times with coarse aggregate.
An allowance must be made for the bulking of damp sand which can be as much as 331/3%. General rule of thumb unless using dry sand allow for 25% bulking.
Materials should be well mixed dry before adding water.
Monday, October 19, 2015
Deep Basement Construction
NB. vertical ground anchors installed through the lowest floor can be used to overcome any tendency to flotation during the construction period
Basement Construction
Thursday, October 15, 2015
Complete Excavation
Basement Excavations - Perimeter Trench Excavations
Basement Excavations Open
In economic terms the costs of plant and manpower to cover the extra excavation, backfilling and consolidating must be offset by the savings made by omitting the temporary support works to the sides of the excavation. The main disadvantage of this method is the large amount of free site space required.
Monday, October 12, 2015
Gabions and Mattresses
Mattress: unit fabrication is similar to a gabion but of less thickness, smaller mesh and stone size to provide some flexibility and shaping potential. Application is at a much lower incline Generally used next to waterways for protection against land erosion where tidal movement and/or water level differentials could scour embankments. Typical sizes, 3.0 m long x 2.0 m wide x 0.15 m thick, up to 6.0 m long x 2.0 m wide x 0.3 m thick.
Types of Soil Nails or Tendons
embankments.
Function: After excavating and removing the natural slope msupport, the remaining wedge of exposed unstable soil is pinned or mnailed back with tendons into stable soil behind the potential slip plane.
Types of Soil Nails or Tendons:
• Solid deformed steel rods up to 50 mm in diameter, located in bore holes up to 100 mm in diameter. Cement grout is pressurised into the void around the rods.
• Hollow steel, typically 100 mm diameter tubes with an expendable auger attached. Cement grout is injected into the tube during boring to be ejected through purpose-made holes in the auger.
• Solid glass reinforced plastic (GRP) with resin grouts. Embankment Treatment ~ the exposed surface is faced with a plastic coated wire mesh to fit over the ends of the tendons. A steel head plate is fitted over and centrally bolted to each projecting tendon, followed by spray concreting to the whole face.
Crib Retaining Walls
Friday, September 11, 2015
Retaining Walls - Construction
Staged post-tensioning to high masonry retaining walls |
Retaining Walls - Masonry Units
- Quetta bonded standard brick units, OR
- Stretcher bonded standard hollow dense concrete blocks.
Monday, September 7, 2015
Climbing Formwork or Lift Casting
Cantilever Retaining Walls
Mass Retaining Walls
Sunday, June 28, 2015
Earth Pressures - Retaining Walls
2. Passive Earth Pressures - these are a reaction of an equal and opposite force to any imposed pressure thus giving stability by resisting movement.
Friday, June 26, 2015
Retaining Walls up to 6-000 High
Design the actual design calculations are usually carried out by a structural engineer who endeavours to ensure that:
1. Overturning of the wall does not occur.
2. Forward sliding of the wall does not occur.
3. Materials used are suitable and not overstressed.
4. The subsoil is not overloaded.
5. In clay subsoils slip circle failure does not occur.
The factors which the designer will have to take into account:
1. Nature and characteristics of the subsoil(s).
2. Height of water table † the presence of water can create hydrostatic pressure on the rear face of the wall, it can also affect the bearing capacity of the subsoil together with its shear strength, reduce the frictional resistance between the underside of the foundation and the subsoil and reduce the passive pressure in front of the toe of the wall.
3. Type of wall.
4. Material(s) to be used in the construction of the wall.
Wednesday, June 24, 2015
Small Height Retaining Walls
Monday, June 22, 2015
Retaining Walls up to 1m High
Pile Testing
1 . Jacking against kentledge placed over test pile.
2. Jacking against a beam fixed to anchor piles driven in on two sides of the test pile.
Saturday, June 20, 2015
Pile Caps
1 . Friction Piles † 1„100 or not less than 3 x pile diameter, whichever is the greater.
2. Bearing Piles † 750 mm or not less than 2 x pile diameter, whichever is the greater.
Wednesday, June 17, 2015
Driven In-situ Piles
Steel Tube Piles
Tuesday, June 16, 2015
Steel Screw Piles
Friday, May 8, 2015
Steel Box and `H' Sections
Thursday, April 23, 2015
Preformed Concrete Piles
Preformed Concrete Piles
Monday, March 16, 2015
Timber Piles
Displacement Piles
Monday, March 2, 2015
Grout Injection Piling
Thursday, February 26, 2015
Replacement Piles
Thursday, February 12, 2015
Piled Foundations - Classification
1. Natural low bearing capacity of subsoil.
2. High water table - giving rise to high permanent dewatering costs.
3. Presence of layers of highly compressible subsoils such as peat and recently placed filling materials which have not sufficiently consolidated.
4. Subsoils which may be subject to moisture movement or plastic failure.
Classification of Piles, piles may be classified by their basic design function or by their method of construction:
Subscribe to:
Posts (Atom)